Toxic & Hazardous Chemicals

Toxic & Hazardous Chemicals mechanical seal selection diagram: pump duties, seal arrangements and API piping plans

Media Overview

Toxic & Hazardous Chemicals — Media Overview

Lethal, toxic and carcinogenic media (liquid chlorine, phosgene, hydrogen cyanide, vinyl chloride monomer, hydrogen sulphide, isocyanates) are sealed so that process fluid has no path to atmosphere in normal operation. This is achieved with a pressurised double seal (API 682 Arrangement 3) whose barrier fluid is held above seal-chamber pressure, with instrumentation that alarms on loss of barrier pressure. For plant-level selection see Chemical Plant, Chlor-Alkali Plant and Polymer & Rubber.

Key Sealing Challenges

  • Containment: barrier pressure is held typically 1.5–2.0 bar above seal-chamber pressure so that inboard leakage is barrier fluid into the process.
  • Barrier fluid compatibility: the barrier must not react with the process: for chlorine, a chlorine-compatible fluid; for isocyanates, an anhydrous plasticiser (DINP or supplier-approved; DOP is REACH-restricted).
  • Metallurgy: dry chlorine attacks titanium (it can ignite); Hastelloy C or Monel are used. Sour H₂S service needs metals to NACE MR0175 / ISO 15156.
  • Moisture: isocyanates form solid polyurea with moisture; a Plan 62 dry-nitrogen quench keeps air humidity off the faces.
  • Instrumentation: Gipfel supplies its Plan 53B and Plan 54 barrier systems fully instrumented, with barrier pressure and level transmitters, alarm and trip; SIL rating is set by the plant’s own safety study.

Which mechanical seal is used on liquid chlorine pumps?

A pressurised double cartridge seal (Arrangement 3) with Hastelloy C or Monel metal parts (no titanium in dry chlorine), SiC vs SiC faces, FFKM secondary seals and a chlorine-compatible barrier fluid on API Plan 53B or Plan 54 is used, with barrier-pressure alarms.

Root-Cause Failure Analysis — Field Example

Symptom: MDI pump seal locks up; white solid deposit on the outboard faces.
  ├── Incorrect Response: "Replace the seal and restart."
  ├── Diagnostic Evidence Required:
  │     ├── Is moist air reaching the faces (polyurea formation)?
  │     ├── Barrier fluid type: anhydrous and compatible with isocyanate?
  │     └── Barrier pressure above seal-chamber pressure at all times?
  └── Engineered Solution:
        ├── Pressurised double seal, Plan 53B or Plan 54.
        ├── Anhydrous plasticiser barrier (DINP or supplier-approved).
        └── Plan 62 dry-nitrogen quench on the atmospheric side.

Frequently Asked Questions

Why is a pressurised double seal used for toxic fluids?

With the barrier above process pressure, any leakage across the inboard faces is barrier fluid into the process, not process fluid outward. Outboard leakage is barrier fluid, which is selected to be non-hazardous and is monitored.

Can titanium be used in chlorine service?

Titanium is suitable in wet chlorine but must not be used in dry chlorine, where it can ignite. Hastelloy C and Monel are used for dry liquid chlorine. Related: Chlor-Alkali · Chemical Plant · Hydrocarbons & Solvents · Acids.


Request a Seal Selection

Send the fluid name and concentration, SDS, temperature, suction and discharge pressure, pump make and model, shaft size and speed to info@gipfelengg.com or use our enquiry form. Gipfel Engineering (ISO 9001:2015, NSIC-registered MSME, Mumbai) designs and manufactures mechanical seals, seal support systems and process pumps.

Equipment solutions: Overhung Pumps · Reactors · Agitators.

Pump Duty & Mechanical Seal Selection Matrix

Typical values for selection guidance only. Final selection is made against the customer duty sheet and the fluid SDS.

Pump duty Fluid Typical temp. Typical pressure (bar) Seal arrangement Faces / elastomer API piping plan
Liquid Chlorine Pump Dry liquid Cl₂ -30 to 40 °C 5–15 bar Double cartridge, back-to-back (pressurised) SiC vs SiC / FFKM; Hastelloy C or Monel API Plan 53B or Plan 54
Phosgene / HCN Pump COCl₂ / HCN -10 to 60 °C 3–15 bar Double cartridge, back-to-back (pressurised) SiC vs SiC / FFKM; Hastelloy C API Plan 53B or Plan 54
VCM Pump Vinyl chloride monomer -10 to 50 °C 5–15 bar Double cartridge, back-to-back (pressurised) SiC vs carbon / FFKM API Plan 53B
Sour Hydrocarbon Pump H₂S-bearing liquid Ambient–120 °C 5–30 bar Double cartridge, back-to-back (pressurised) SiC vs SiC / FFKM; metals to NACE MR0175 API Plan 53B
Isocyanate (MDI / TDI) Pump MDI / TDI 25–60 °C 3–10 bar Double cartridge, back-to-back (pressurised) SiC vs carbon / FFKM Plan 54 anhydrous plasticiser barrier + Plan 62 dry N₂
Aniline / Toxic Amine Pump Aniline Ambient–100 °C 3–10 bar Double cartridge, back-to-back (pressurised) SiC vs carbon / FFKM API Plan 53A/53B

Reviewed by Gipfel Engineering’s technical team.

Technical Information Disclaimer

The information on this page, including process descriptions, flow diagrams, operating ranges, seal arrangements, materials and piping plans, is general technical guidance for information only. Values shown are typical industry ranges, not guaranteed ratings or specifications of any Gipfel Engineering product. Each application differs. Seal selection, material compatibility, installation and operation must be verified by qualified personnel against the specific equipment data sheet, process conditions, applicable codes and the pump manufacturer’s instructions. A binding recommendation is given only in a written quotation or technical offer from Gipfel Engineering.

References to standards (such as API 682, ISO 21049, ISO 3069, FDA 21 CFR 177.2600 and NACE MR0175 / ISO 15156) describe common industry practice. They do not mean that any product is certified, qualified or approved to that standard unless this is confirmed in writing for a specific order. Third-party company and product names, including “equivalent to” references, are used for identification only and remain the trademarks of their owners. No affiliation, endorsement or OEM approval is implied.

Compliance with safety, hazardous-area, environmental and statutory requirements at the user’s site remains the responsibility of the plant owner or operator. To the extent permitted by law, Gipfel Engineering accepts no liability for loss or damage arising from reliance on this general information without a confirmed written recommendation. Content may change without notice.

Table of Contents